Home › 90 MW standby and peak-load boiler house retrofit on the Baltic coast

90 MW standby and peak-load boiler house retrofit on the Baltic coast

A boiler house retrofit brings new equipment and supporting structures into an existing industrial building. MESTIL developed the structural design for the extension and alteration of a 90 MW standby and peak-load boiler house on the Baltic coast. The investment is intended to support the development of Baltic offshore wind energy.

Our task was to adapt the old facility to accommodate new boilers and their associated installations. The scope included site surveys, foundation and support design, access platforms and BIM coordination.

Surveying the existing boiler house before the retrofit

We started by establishing the building’s actual geometry. The positions of beams, columns and existing installations influenced the layout of the new equipment and its supporting structures.

We used photogrammetric imagery together with measurements taken on site. These records provided a basis for representing the existing building and coordinating the proposed works with its actual geometry. The design could therefore respond to the conditions identified at the facility.

An engineer measuring the existing steel beams on the roof before the rebuild
A survey of the existing beams comes before every design decision.
Insulated district heating pipelines marked OCV4 and OCV5, carried by a steel structure
Point cloud of the existing pipe rack with insulated pipelines

New boilers, foundations and access platforms

Installing new boilers involves more than finding sufficient floor space. The design also needs to address load transfer, supports for process installations and access for equipment operation and maintenance.

Our structural scope included new foundations, supporting structures and access platforms. These elements had to fit the existing building layout while working around boilers, pipework and other installations.

In an industrial retrofit, every new element has interfaces with existing supports, space constraints and process requirements. Foundations and platforms therefore need to be coordinated with the other engineering disciplines.

3D model of the boiler house – steel frame, tanks and pipelines on several levels
3D model of the boiler house – steel supporting structure, process pipelines and stack

BIM coordination for the boiler house retrofit

MESTIL also acted as BIM coordinator. Bringing the proposed structures and installations together in a shared model environment enabled the team to assess spatial interfaces, identify clashes and coordinate solutions across disciplines.

Within the constraints of an existing boiler house, this approach supports earlier design decisions and helps reduce the risk of costly changes during construction. The model supported coordination between the new equipment, access platforms and the building structure.

Building permit design for the extension and alteration

The work resulted in building permit design documentation covering the extension and alteration of the boiler house. The investment obtained a building permit.

Model of the supporting structure – lattice tower, pipeline supports and foundations
Model of the boiler house structure with floors, marked grid lines and pile foundations
The new structure lands on its own piles, beside the foundations of the existing plant.

MESTIL support for industrial building upgrades

We support clients installing new equipment in existing industrial buildings, from surveys and structural assessment to calculations, new structural elements and coordination of the design documentation.

Planning a boiler house retrofit or an industrial facility upgrade? Explore our structural design services, BIM coordination and technical consultancy. Contact MESTIL to discuss the scope of your investment.